Calculate your Sealed Unit Material and Labour Costs

Enter your individual IG component costs below to calculate your own sealed unit material costs per unit you produce. Once you have entered all the figures, click the 'Recalculate' button at the top right or bottom left of this page. Your current sealed unit material costs per unit and guide unit selling prices will then appear in the summary at the top and bottom of this page. There is also the option for you to add labour costs if required.

Recalculate

Current Cost Per Sealed Unit (£):
Sealant -
PIB -
Spacer -
Corner Keys -
Desiccant -
Cloth Tape -
Glass -
Manpower per unit -
Total -
Guide to selling price to achieve margins as follows:
20% -
30% -
40% -
50% -
60% -
70% -
80% -
Please note: No wastage or energy costs included.
Sealed Unit Dimensions      
Unit height (Metres)   Unit Width (Metres)
Spacer Costs      
Stillage / Box Price (£)   Cost per metre -
Stillage / Box Quantity
(metres)
  Cost Per Sealed Unit -
Corner Key Costs      
Box Price (£)   Cost per key -
Box Quantity   Cost per sealed unit -
Desiccant Costs*      
Box Price (£)   Cost per Kg -
Box Volume (Kg)   Cost Per Sealed Unit -
* - Desiccant costs estimated on filling 50% of the total bar length.
Please note that although you are advised to fill 3-4 sides when using warm edge spacer bar, the internal dimensions of warm edge bar are smaller so this amounts to a similar volume of desiccant.
Sealant Costs      
Block Price (£)   Expected Bond Area (mm) -
Block Volume
(Litres per block)
  Mitre Run Per Litre -
Price Per Litre -   Price Per Metre -
Amount Deducted
from Bar (mm)
  Cost Per Sealed Unit -
Unit Cavity Size (mm)      
PIB Costs      
Cost per Kg (£)   Cost Per Sealed Unit -
Cost per linear metre -      
Cloth Tape Costs      
Cost per roll   Cost per metre -
No. metres per roll   Cost Per Sealed Unit -
Glass Costs (per square metre)      
Annealed (£)   Low-E Glass (£)
         
Labour Costs      
No. of sealed units your business produces p/week   No. of staff
No. of hours staff work p/week (each)   Wages per staff member per hour
Total Manpower Cost per Unit -      

Please note:

Enter a zero value into the costs that are not required. E.g. for warm edge units made with foam spacer take out the costs of corner keys and desiccant.

Current Material Cost Per Sealed Unit (£):
Sealant -
PIB -
Spacer -
Corner Keys -
Desiccant -
Cloth Tape -
Glass -
Total -
Guide to selling price to achieve margins as follows:
20% -
30% -
40% -
50% -
60% -
70% -
80% -
Please note: No Labour costs, energy costs, or wastage included.
Current Cost Per Sealed Unit (£):
Sealant -
PIB -
Spacer -
Corner Keys -
Desiccant -
Cloth Tape -
Glass -
Manpower per unit -
Total -
Guide to selling price to achieve margins as follows:
20% -
30% -
40% -
50% -
60% -
70% -
80% -
Please note: No wastage or energy costs included.

Recalculate

Useful information and cost implications

Consider the cost of corner keys:


Standard Corney Key
x 4/5 times the cost =
Gas Corner Key

A Gas Hole Punch Tool Kit could save you the cost of gas corner keys (see web link and photos below):


Please note: Collars and sleeves will be required for this method, but the cost of collars and sleeves is minimal in comparison to the cost of gas corner keys.

Multigas Fillers:

See Thermoseal Group's own range of Gas Fillers for all levels of IG sealed unit production (click link below):